VAK Russia 2.1.7 UDC 69.05

ENTROPY‑TIME DIAGNOSTICS OF DEVIATIONS IN CONSTRUCTION SCHEDULING Entropy‑time diagnostics of deviations in construction scheduling

Published in Construction production · Issue 3, 2026 · ELocator: CP0095 · Rubric: Original articles
DOI: https://doi.org/10.29039/2658-5340-2026-3-CP0095 · EDN: JPXIVB
Received: 16.09.2026 Accepted: 19.09.2026 Published: 29.09.2026 Language of publication: ru-RU
The article examines the problem of integral assessment of the state of a construction flow, in which entropy indicators are supplemented by deterministic parameters of the schedule. The aim of the work is to develop an entropy‑time classification of criticality, which ensures the transformation of multidimensional diagnostic information into an unambiguous management signal. The methodological basis consists of system analysis, the theory of information entropy, network planning methods, and elements of automatic control theory. It has been shown that global macroentropy and local Shannon entropy alone do not allow for an unambiguous determination of the structural consequences of accumulated deviations: a critical increase in entropy can be caused either by a general decline in productivity or by a local malfunction in a system with a significant time reserve. A four‑level criticality scale (I – normal, II – warning, III – danger, IV – crisis) has been proposed, combining the time, macroentropy, and microentropy axes of diagnostics. Threshold values of entropy have been formalized for projects of varying technological rigidity; a binary indicator of local chaos has been introduced; and an identification matrix for the integral level of criticality has been constructed. An automated assessment algorithm has been developed, comprising five stages: data extraction, calculation of time‑based and macro‑entropy levels, accounting for local chaos, integral assessment, and output of the control vector into the adaptive control loop.
construction flow, calendar planning, entropy, critical path, time reserve, adaptive management
Text References

1. Vozhova E. V., Dyshlovoy I. N. Primenenie metoda kriticheskogo puti (CRM) v upravlenii vremennymi ramkami proektov // Ekonomika i predprinimatel'stvo. —2025. — № 6. — S. 969-972. DOIhttps://doi.org/10.34925/EIP.2025.179.6.174. EDN: https://elibrary.ru/WZQAKB

2. Yang J.-B., Kao C.-K. Critical path effect based delay analysis method for construction projects // International Journal of Project Management. — 2012. — V. 30, I. 3. — PP. 385-397. DOI:https://doi.org/10.1016/j.ijproman.2011.06.003.

3. Adamec D. Yu., Amelina K. E., Burkov V. N., Hodunov A. M. Zadachi kalendarnogo planirovaniya po kriteriyu maksimizacii summarnogo vzveshennogo ob'ema vypolnennyh rabot // Sistemy upravleniya i informacionnye tehnologii. — 2018. — № 4. — S. 20-25. EDN: https://elibrary.ru/YPEYIP

4. Bolotin S. A., Al'-Zhanabi M. A., Bohan H. A. Prognozirovanie okonchaniya stroitel'stva na osnove modelirovaniya nelineynoy zavisimosti ot zaderzhek otdel'nyh rabot // Vestnik grazhdanskih inzhenerov. — 2022. —№ 2. —S. 83-90. DOIhttps://doi.org/10.23968/1999-5571-2022-19-2-83-90. EDN: https://elibrary.ru/OGVLBZ

5. Hsu P, Aurisicchio M, Angeloudis P, Whyte J. Understanding and visualizing schedule deviations in construction projects using fault tree analysis //. Engineering, Construction and Architectural Management. — 2020. — Vol. 27 No. 9 — Pp. 2501–2522, doi: https://doi.org/10.1108/ECAM-01-2020-0058 EDN: https://elibrary.ru/TUWIOA

6. Yang J.-B., Kao C.-K. Critical path effect based delay analysis method for construction projects // International Journal of Project Management. — 2012. — V. 30, I. 3. — Pp. 385-397. DOI:https://doi.org/10.1016/j.ijproman.2011.06.003.

7. Tazhibayev A. Mathematical modeling and validation of predictors of schedule deviations in trunk pipeline construction based on daily production data // Universum: technical sciences. — 2026. — №4 (145). URL: https://7universum.com/ru/tech/archive/item/22597 DOI: https://doi.org/10.32743/UniTech.2026.145.4.22597

8. Mihaylova E.V. Opredelenie prodolzhitel'nosti vozvedeniya zdaniy i sooruzheniy v usloviyah neopredelennosti // Stroitel'noe proizvodstvo. — 2020. — № 1. — S. 12-16. DOI: https://doi.org/10.54950/26585340_2020_1_12; EDN: https://elibrary.ru/LLMNFV

9. Gacevski V., Lazarevska M., Zafirovski Z. Ranking of total time reserves for determination of the critical path in fuzzy network plan // Journal of Applied Engineering Science. – 2024. – T. 22. – №. 2. – S. 297-302. DOI: https://doi.org/10.5937/jaes0-50535; EDN: https://elibrary.ru/IBGWDV

10. Car'kova E.V. Metody upravleniya proektami v usloviyah informacionnoy neopredelennosti // Pravovaya informatika. — 2019. — №4. EDN: https://elibrary.ru/VNTVQO

11. Mihal'chenko O.Yu. Bifurkacii v kalendarno-setevom planirovanii stroitel'nyh proektov: metody prognozirovaniya i adaptivnogo upravleniya // Izvestiya KGASU. – 2025. – № 1(71). – S. 122-129, DOI:https://doi.org/10.48612/NewsKSUAE/71.11, EDN: https://elibrary.ru/MHSATY

12. Christodoulou S., Ellinas G., Aslani P. Entropy-based scheduling of resource-constrained construction projects // Automation in Construction. — 2009. — Vol. 18. Issue 7. —Pp. 919-928. https://doi.org/10.1016/j.autcon.2009.04.007.

13. Pourrahimian E., Salhab D., Hamzeh F., AbouRizk S. Entropy-centric framework for understanding and managing project dynamics in construction // Automation in Construction. — 2025. — V. 170. 105928. DOI:https://doi.org/10.1016/j.autcon.2024.105928. EDN: https://elibrary.ru/ZGHOLC

14. Nie X., Li M., Lu J., Wang B. Research on Buffer Calculation Model of Critical Chain Based on Adjacency Information Entropy // Buildings. — 2023. — Vol.13. — Pp.942. https://doi.org/10.3390/buildings13040942 EDN: https://elibrary.ru/UCZCZT

15. Peng J.-l.; Peng C. Buffer Sizing in Critical Chain Project Management by Brittle Risk Entropy // Buildings. — 2022. — Vol. 12. Pp. 1390. https://doi.org/10.3390/buildings12091390 EDN: https://elibrary.ru/BIVOVY

16. Bai X.-P., Zhang X.-W. A Novel Evaluation Method for Building Construction Project Based on Integrated Information Entropy with Reliability Theory // The Scientific World Journal. — 2013. — 573014. https://doi.org/10.1155/2013/573014

17. Liu D., Yu L., Li B. Fuzzy-Entropy Theory Comprehensive Evaluation Method and Its Application in Building Construction Safety // Procedia Engineering. — 2012. — Vol. 43. — Pp. 137-142. https://doi.org/10.1016/j.proeng.2012.08.024.

18. Lapidus A.A., Mihaylova E.V. Entropiya i dinamika otkloneniy v upravlenii kalendarnym planom stroitel'stva // Izvestiya vysshih uchebnyh zavedeniy. Stroitel'stvo. — 2026. — № 6 (810). — S. 85-97. DOI:https://doi.org/10.32683/0536-1052-2026-810-6-85-97 EDN: https://elibrary.ru/QFSBTD