VAK Russia 2.1.7 UDC 69 VAK Russia 2.1.14

THE IMPACT OF WORK TECHNOLOGY ON THE DURATION AND EFFICIENCY OF THE CONSTRUCTION OF AN ENERGY FACILITY The impact of work technology on the duration and efficiency of the construction of an energy facility

Published in Construction production · Issue 4, 2025 · ELocator: CP0018 · Rubric: Original articles
DOI: https://doi.org/10.29039/2658-5340-2025-4-CP0018 · EDN: XRSQSM
Received: 31.10.2025 Accepted: 30.11.2025 Published: 24.12.2025 Language of publication: ru-RU
Introduction. New technological and organizational solutions are used in the construction of energy facilities, which can reduce resource consumption and the duration of works. However, the issue of the economic consequences of changing work deadlines during the introduction of new technologies has not been investigated. The purpose of the study is to determine the calculated effect of reducing the duration of construction of an energy facility. Methods. To study the construction schedule, a conditional electric power generation facility with a capacity of 1 GW was considered. With the help of a comparative analysis, the likely scenarios for the development of the construction site are considered, taking into account the effects that the investor and contractor have when the duration of construction changes. Possible mutual penalties and bonuses incurred by partners in the course of business activities and joint work on the implementation of the project are taken into account. Results. As a result of the research, the effects of early commissioning of power units have been calculated, as well as possible losses if the schedule is behind schedule and if the contractual deadlines for commissioning units are disrupted. Conclusions. Recommendations are given on the organization of the introduction of new technologies in the design and construction of energy facilities of various types at various stages of the life cycle.
energy facilities, duration, critical path, construction, technology, commissioning
Text References

1. Morozenko A.A. Improving the Efficiency of Organizational and Technological Solutions when Constructing Nuclear Power Plants on the Basis of Contemporary Russian and Foreign Experience / A.A. Morozenko, I.E. Voronkov.// Promyshlennoe i Grashdanscoe stroitelstvo. – 2014. – V. 10, – p. 74-79 (Rus). EDN: https://elibrary.ru/SWMCKF

2. Morozenko A.A. Scientific Approaches to Selecting the Assembly Block Configuration for VVER NPP Reactor Buildings / A.A. Morozenko, A.V. Baukin // Stroitelnoe proizvodstvo – 2025. – V. 2., – pp. 50-54 (Rus). DOI: https://doi.org/10.54950/26585340_2025_2_50; EDN: https://elibrary.ru/WHNYGQ

3. Korotkikh D.N. Review of Experience in the Construction of NPP Using Modular Structures with External Sheet Reinforcement / D.N. Korotkikh and other. // Vestnik MGSU. – 2024, – V. 10, – Pp. 1696-1712 (Rus). DOI: https://doi.org/10.22227/1997-0935.2024.10.1696-1712; EDN: https://elibrary.ru/AUFQZV

4. Morozenko A.A. Organizational and Technological Aspects of Large-scale Construction of Nuclear Power Plants. / A.A. Morozenko, A.A. Shashkov // Nauka i Business: puti razvitiya. – 2019. – V. 5, – pp. 28-33 (Rus). EDN: https://elibrary.ru/IFASBL EDN: https://elibrary.ru/YEMCPG

5. Dorf V.A. The Retained Steel Fiber Concrete Formwork as a Bearing Element of Ferroconcrete Structures / V.A. Dorf and other. // Severny region: nauka, obrazovanie, kultura. – 2015, – V.2. – 148-153 (Rus). EDN: https://elibrary.ru/VCTZED

6. Subbotin A.S. Possibility of Using Public-Private Partnership in the Construction of Thermal Power Plants. / A.S. Subbotin, D.S. Iashina // Novie technologii v stroitelstve. – 2024. – V. 1 – Pp. 29-33 (Rus). DOI: https://doi.org/10.24412/2409-4358-2024-1-29-33; EDN: https://elibrary.ru/UBASYU

7. Adam A. Aggregation of factors causing cost overruns and time delays in large public construction projects / A. Abderisak, P.-E. B. Josephson,G. Lindahl. // Engineering, Construction and Architectural Management. – 2017 – V. 24, Issue 3, – Pp. 393-406. – https://doi.org/10.1108/ECAM-09-2015-0135.

8. Durdyev S. Causes of delays on construction projects: a comprehensive list Available to Purchase / S. Durdyev, M. R. Hosseini // International Journal of Managing Projects in Business – 2020 – 13 (1): – Pp. 20–46. – https://doi.org/10.1108/IJMPB-09-2018-0178.

9. Sovacool B.K. Beyond economies of scale: Learning from construction cost overrun risks and time delays in global energy infrastructure projects / B. K. Sovacool, H. Ryu. // Energy Research & Social Science. – 2025 – V. 123. – 104057. – https://doi.org/10.1016/j.erss.2025.104057.

10. Fouladvand J. Infrastructure and governance: Prioritizing energy security dimensions for community energy systems. / J. Fouladvand, Y. Sarı, A. Ghorbani.// Energy Research & Social Science. – 2024 – V. 116. – 103676. – https://doi.org/10.1016/j.erss.2024.103676.

11. Sovacool B.K. An international comparative assessment of construction cost overruns for electricity infrastructure. / B. K. Sovacool, A. Gilbert, D. Nugent // Energy Research & Social Science. – 2014 – V. 3. – Pp. 152-160. – https://doi.org/10.1016/j.erss.2014.07.016.

12. Park J.E. Schedule delays of major projects: what should we do about it? / J. Eun. Park // Transport Reviews –2021. – V. 41, – Issue 6, – Pages 814-832. – https://doi.org/10.1080/01441647.2021.1915897 EDN: https://elibrary.ru/FDEXLW

13. Lyons R.C. Time to build: Rules-based planning and construction project duration in Dublin / Ronan C. Lyons, Éamonn Sweeney. // Journal of Housing Economics. – 2025. – https://doi.org/10.1016/j.jhe.2025.102089. EDN: https://elibrary.ru/JPOSQL

14. Gandhi S. Too slow for the urban march: Litigations and the real estate market in Mumbai, India. / S. Gandhi, V. Tandel, A. Tabarrok, S. Ravi // Journal of Urban Economics. – 2021 – V. 123. – 103330. – https://doi.org/10.1016/j.jue.2021.103330. EDN: https://elibrary.ru/YDICRD

15. Gilbert A. Cost overruns and financial risk in the construction of nuclear power reactors: A critical appraisal / A. Gilbert, B. K. Sovacool, P. Johnstone, A. Stirling. // Energy Policy, – 2017 – V. 102. – Pp. 644-649. – https://doi.org/10.1016/j.enpol.2016.04.001.

16. Wheatley S. Reassessing the safety of nuclear power / S. Wheatley, B. K. Sovacool, D. Sornette // Energy Research & Social Science. – 2016 – V. 15 – Pp. 96-100. – https://doi.org/10.1016/j.erss.2015.12.026.

17. Pavlov A. S. Time Reservation during Construction of Large-scale Projects / A.S. Pavlov, R.V. Ostrovsky // Construction and Architecture. – 2024 – V. 12, No 2. – DOIhttps://doi.org/10.29039/2308-0191-2024-12-2-3-3 (Rus). EDN: https://elibrary.ru/MHATEP

18. Al-Tameemi Kh. Sh. The Impact of Schedule Compression Techniques on Construction Project Timelines: A Case Study in Basrah, Iraq. / Kh. Sh. Al-Tameemi // The Open Civil Engineering Journal. – 2025 – V. 19. – https://doi.org/10.2174/0118741495360335241205110710. EDN: https://elibrary.ru/HYAYZC

19. Ballesteros-Pérez P. Non-linear time-cost trade-off models of activity crashing: Application to construction scheduling and project compression with fast-tracking / P. Ballesteros-Pérez, K. M. Elamrousy, C. González-Cruz // Automation in Construction. – 2019 – V. 97 – Pp. 229-240. – https://doi.org/10.1016/j.autcon.2018.11.001.

20. Ardahsasta N. Schedule optimization of construction project by calculating float loss cost Available to Purchase. / N. Ardahsasta, O. Gondokusumo // AIP Conference Proceedings. – 2023 – 2680, 020035 (2023). – https://doi.org/10.1063/5.0126133.